The Okemos Addition
Addition · 2024

The Okemos Addition

Okemos, MI

Sq ft

740

Budget

$180k–$220k

Duration

14 weeks

Crew

Crew 3 · Lead: Tom

A 740 sq ft family-room addition with a tie-in to the existing roof line and an open pass-through to the kitchen.

Phase by phase

  1. WK 1-2

    Permit + prep

    Drawings submitted, neighborhood notification, site protection, material stage.

  2. WK 3-4

    Foundation

    Excavation, footings poured, block wall, sill plate set.

  3. WK 5-7

    Framing + dry-in

    Walls, roof tie-in, wrap, windows installed. Rough mechanicals started.

  4. WK 8-10

    MEP + insulation

    Rough inspection, spray foam, drywall hung and finished.

  5. WK 11-13

    Finish carpentry

    Trim, flooring, paint, cabinetry. Fixtures installed.

  6. WK 14

    Punch + walkthrough

    Final inspection, client walk-through, warranty packet delivered.

Gallery

"TRG showed up when they said they would, every single week. The schedule held to the day."
— S. Reynolds · Homeowner