Addition · 2024
The Okemos Addition
Okemos, MI
Sq ft
740
Budget
$180k–$220k
Duration
14 weeks
Crew
Crew 3 · Lead: Tom
A 740 sq ft family-room addition with a tie-in to the existing roof line and an open pass-through to the kitchen.
Phase by phase
- WK 1-2
Permit + prep
Drawings submitted, neighborhood notification, site protection, material stage.
- WK 3-4
Foundation
Excavation, footings poured, block wall, sill plate set.
- WK 5-7
Framing + dry-in
Walls, roof tie-in, wrap, windows installed. Rough mechanicals started.
- WK 8-10
MEP + insulation
Rough inspection, spray foam, drywall hung and finished.
- WK 11-13
Finish carpentry
Trim, flooring, paint, cabinetry. Fixtures installed.
- WK 14
Punch + walkthrough
Final inspection, client walk-through, warranty packet delivered.
Gallery
"TRG showed up when they said they would, every single week. The schedule held to the day."